Samsung Electronics Co

Construction Overview

2023
Pyeongtaek P3 PH4 Piping Hookup Construction
Hwaseong 17L PN2 Purifier, HPA FILTER Hydrogen Piping Construction
Hwaseong 17L LP Air System and N2 Purifier Expansion Project
2022
Pyeongtaek P3 PH3 Piping Hookup Construction
Pyeongtaek P3 PH2 Piping Hookup Construction
Pyeongtaek P3 PH1 Piping Hookup Construction
Hwaseong General Piping Duct Maintenance Work
Pyeongtaek General Piping Duct Maintenance Work
Hwaseong Hook-up Piping Construction
Hwaseong RETROFIT Site
2021
Hwaseong RETROFIT Site/dd>
Pyeongtaek P2 Upper East Piping Hookup Construction
Pyeongtaek P2 Upper East Piping Hookup Construction
Hwaseong Hook-up Piping Work
2020
Hwaseong Low-pressure Purifier Pressure Vessel Replacement Work
2019
Hwaseong Hook-up Piping Work
Hwaseong GAS&PCW Piping Construction
2018
Hwaseong GAS&PCW Piping Construction
Pyeongtaek P-PJT Hook-up 2nd Piping Construction
Hwaseong Hook-up Piping Construction
Pyeongtaek P1 Hook-up Maintenance Work
VACUUM Piping Construction
2017
Pyeongtaek P1-2 (upper floor) FT Hook-up Construction
Hwaseong LN2 Piping Construction
Pyeongtaek P-PJT East-side Secondary Pipeline Hook-up Construction
VACUUM Piping Work

Samsung C&T Corporation

Construction Overview

2023
Pyeongtaek P4 PH2 General Piping Work
Pyeongtaek P4 PH2 GAS/PCW Temporary Piping Construction
Pyeongtaek P4 PH1 General Piping Work
Pyeongtaek P4 PH1 GAS/PCW 2 Tools (SUP) Piping Construction
Pyeongtaek P4 PH1 Chemical Piping Construction
Asan FAB A6-IT PJT GAS&PCW 2 Tools
2022
Pyeongtaek P4L Phase1 BULK GAS Buried Pipeline Construction
Pyeongtaek P4 PH1 GAS 1 Tool (FAB) Piping Construction
Pyeongtaek P3L PH4 GAS 1 Tool
Pyeongtaek PH3 GAS 1 Tool among P3 Ph3
2021
Pyeongtaek P3 New Construction (S-SUP PCW 1 Tool)
Pyeongtaek P3 New Construction PCW 1 Tool
Pyeongtaek P3 New Construction PH1 GAS&PCW Construction
2020
Pyeongtaek P2 GAS&PCW 1 Tool (same as below)
Pyeongtaek P2 New Construction Lower Western Part (Gas)
Pyeongtaek P2 GAS&PCW 2 Tool (same as above)
Hwaseong 18L E-PJT GAS&PCW Unfinished Piping Construction
Samsung C&T STS Piping Automatic Welding Test Service
2019
Asan Cleanroom Finishing Work (FAB Building) GAS &PCW Work 2 Tools/dd>
Samsung C&T High-tech Piping Welding Automation Technology Development (STS) Research Service
2018
Pyeongtaek P2 New Construction GAS 1 Tool
Hwaseong E-PJT Temporary Nitrogen Piping Construction
Hwaseong DSR Secondary GAS&PCW Piping Construction
Hwaseong 18L E-PJT GAS&PCW Piping Construction
2017
Asan Campus 1 7-1L T-PJT GAS&PCW 3 Tools
Pyeongtaek P-PJT PH-4 GAS&PCW Piping Construction
Pyeongtaek P-PJT PH-3 GAS&PCW Piping Construction
Pyeongtaek P-PJT PH-2 GAS&PCW Piping Construction
Hwaseong E-PJT Machinery & Equipment Construction 7NANO GAS&PCW Piping Construction
Hwaseong DSR GAS&PCW Maintenance Work
Hwaseong 17L FAB Lower Finishing Work

SK Hynix Corporation

Construction Overview

2023
M15 HOOK-UP Piping Construction
Cheongju 3rd Campus Investment, Relocation H/U Construction
Cheongju 1st Campus Investment, Relocation H/U Construction
2022
M15 HOOK-UP Piping
Icheon M16 HOOK-UP Construction
Icheon M10F HOOK UP Piping Construction
Cheongju 3 Campus Investment, Relocation H/U Construction
Cheongju 1 Campus Investment, Relocation H/U Construction
2021
M16 HOOK-UP Construction
Icheon M14 HOOK-UP Corporation
Icheon M10F HOOK UP Piping Construction
Cheongju 3 Campus Investment, Relocation H/U Construction
Cheongju 1 Campus Investment, Relocation H/U Construction
2020
M16 HOOK-UP Construction
Icheon D-F HOOK UP Piping Construction
Cheongju M11,M12 Investment and Relocation Equipment HOOK-UP Construction
Icheon M14 HOOK-UP Construction
Cheongju 1 Campus Investment and Relocation H/U Construction
2019
DI-F HOOK UP Piping Construction
Cheongju M15 PH-1 HOOK-UP Piping Construction
Icheon M14 HOOK-UP Construction
Cheongju M11,M12 Investment and Relocation Equipment HOOK-UP Construction
Cheongju 1 Campus Investment and Relocation H/U Construction
2018
DI-F HOOK UP Piping Construction
Cheongju M15 PJT 5D H/U Corporation
Cheongju M15 PH-1 HOOK-UP Piping Construction
Icheon M14 HOOK-UP Construction
Cheongju M11,M12 Investment and Relocation Equipment HOOK-UP Construction
Cheongju 1 Campus Investment and Relocation H/U Construction
2017
DI-F HOOK UP Piping Construction
Icheon M14 Hook-up Construction
Cheongju M11,M12 Investment and Relocation Equipment HOOK-UP Construction
Cheongju 1 Campus Investment and Relocation H/U Construction

SK Ecoplant Co., Ltd.

Construction Overview

2022
Cheongju M15 Ph-2 Additional Construction
Cheongju M15 Ph-2 Piping Construction/dd>
2021
Cheongju M11 Element Analysis Room Expansion Piping Construction
Icheon M16 Ph-2 Piping Construction
Icheon M16 Ph-1C Piping Construction
2019
Icheon M16 Ph-1 Piping Construction
2018
Cheongju C1 Mask Shop 5th floor Piping Construction
2017
Cheongju M15 FAB/CUB Project Piping Construction
Icheon M14 Side Fab Construction
Icheon M14 Ph-2B CAPA-UP Construction
Icheon M14 Ph-2B Project Main Construction
Cheongju C1 Mask Shop Construction
Cheongju C1 Mask Shop Construction UT Piping Demolition Work
High Selectivity Phosphoric Non-acid Settlement_SIDE FAB

Samsung Display Co., Ltd.

Construction Overview

2023
SPR Cheonan Asan Campus
2021
2021 SDC 1Q-4Q Asan/Cheonan Campus and Green Center Construction
2018
Samsung SDC Maintenance Work in 2018
2017
Samsung Display Ghiheung SR5 Mechanical Room Old Water Piping Replacement
SDC maintenance in 2017

Samsung Heavy Industries & Construction Co., Ltd.

Construction Overview

2023
Samsung Heavy Industries Pyeongtaek P4 PH2 Rack & General Piping Construction
2021
Samsung Heavy Industries Pyeongtaek Campus V2L FSF High Purity, PCW Facility Construction

Samsung SDI Co., Ltd.

Construction Overview

2019
Samsung SDI Cheonan Plant Facilities (Piping, Ducting, Firefighting Equipment)
Samsung SDI M3 PJT Hook-Up Additions
Samsung SDI Dormitory Cooling Tower Piping Replacement Construction
2018
Samsung SDI Positive. Negative RTR HOOK-UP (Piping, Ducting)
Construction Samsung SDI M3 Hook-up(Piping, Ducting) Construction